Work in Progress:
Working on pile caps and grade beams. Plan to start column line 17 (Southern most column line) next week.
Started working on forming elevator #2 (South).
Pouring elevator #1 second lift (North) today.
Continuing the installation of the basement…
March 24, 2016
Work in Progress:
First floor restroom and offices duct layout is complete with HVAC piping and duct installation has begun.
Room 101 & 104 electrical rough-in is at 90% complete.
Machine Shop electric panel installed and completed on Saturday 3/19.
Room 223 electrical…
March 24, 2016
Work in Progress:
Steam piping in the 3rd floor east mechanical room is 20% complete.
Steam condensate lines for the steam station and AHU#1 are in progress.
Started installation of piping and duct work from AHU#2 in the 3rd floor west mechanical room to the addition has…
March 24, 2016
Senior Research Fellow Quan Li, Ph.D., and his research group at 91ֿ’s Liquid Crystal Institute®, in the College of Arts and Sciences, have published a research article in the March 17 issue of Nature that could lead to a variety of breakthrough device…
March 17, 2016
Work in Progress:
Chilled water service in the 3rd floor east mechanical room is 95% complete by EOB on 3/18. Will be ready for cooling system startup on 4/15.
Currently insulating the chilled water pipes in the 3rd floor wast mechanical room.
Steam reducing station…
March 17, 2016
Work in Progress:
New restroom plumbing rough-in nearly complete.
Sheet metal duct rough-in has begun on the first floor and the new restroom areas.
Electrical floor boxes are 75% complete in 223.
Sanitary drain and toilet carriers are complete in the second floor.
3rd…
Image
March 16, 2016
91ֿ Day at the Cleveland Film Festival (CIFF) is slated for April 6 at Tower City Cinemas in downtown Cleveland. 91ֿ is a sponsor of the festival and members of the 91ֿ community will receive $2 off any ticket to a film showing on that day. Kent…
March 16, 2016
The Wick Poetry Center at 91ֿ will expand its successful Traveling Stanzas project with $125,000 in new funding from the John S. and James L. Knight Foundation, as part of its Knight Arts Challenge.
The Knight Arts Challenge funds ideas that…