10/03- Williams Hall/ISB Construction Updates
	
 
  
    
  
          
            ISB
Work in Progress
	- Brick work along line 17, from B to G is in progress.
 
	- Continue retaining wall along line 8.
 
	- Continue curtain wall installation at the northeast side.
 
	- Finalize pre cast and brick work along A line.
 
	- Continue the pouring of the hydraulic slab on the east side, lines 14 to 17.
 
	- CMU installation in penthouse completed.
 
	- Start backfilling for slab on grade east side of the building, lines 14 to 11.
 
	- Start Hydraulic slab on the east side of the building, lines 8 to 11.
 
	- Start CMU wall in basement, lines 1 to 7.
 
Looking Forward
	- Continue pre cast and brick work along line 17, from B to G.
 
	- Pour Hydraulic slab on the east side of the building, lines 14 to 17.
 
	- Finalize installation of the CMU in penthouse.
 
	- Continue CMU wall in basement, lines 1 to 7.
 
	- Continue hydraulic slab on the east side of the building, lines 8 to 11.
 
	- Continue backfilling for slab on grade, east side of the building, lines 14 to 17.
 
Williams Hall
Work in Progress
	- Continue piping work for steam station in mechanical room.
 
	- Ductwork installation on the east side of the building, 1st floor and 2nd floor from lines 1 to 17 is in progress.
 
	- Continue plumbing work for W3: roof drains, storm lines, etc..
 
	- Continue electric rough installation in basement, and 2nd floor lines 1 to 17.
 
	- Continue duct work installation in 1st floor east side of the building.
 
	- Continue final painting concrete.
 
	- Finalize drywall for W3.
 
	- Finalize installation of steel for exhaust fans on roof for W3.
 
	- Start painting walls for W3.
 
Looking Forward
	- Continue piping work for steam station in mechanical room.
 
	- Continue ductwork installation on the east side of the building, 1st floor and 2nd floor from lines 1 to 17.
 
	- Continue plumbing work for W3.
 
	- Continue electric rough installation in basement.
 
	- Continue final painting concrete.
 
	- Continue installation of mill work for W3.
 
	- Continue fireproofing in penthouse and 2nd floor on the east side of the building.
 
 
      
    
    
 
  POSTED: Monday, October 3, 2016 09:43 AM
 
    
        