ISB
Work in Progress
- 
	
Continue pre cast and brick work along G line, lines 8 to 17.
 - 
	
Continue curtain wall installation at the east side of the building.
 - 
	
Continue monitor framing and glass at the north side of the building.
 - 
	
Continue last back filling in the east section of the building.
 - 
	
Last hydraulic slab pouring in the east side of the building is in progress.
 - 
	
Start slab on grade pouring on the north side, and 2” topping, from lines 1 to 7.
 - 
	
Start slab on grade pouring from lines 13 to 17, and 2” topping from lines 7 to 17.
 - 
	
Start framing for penthouse panels.
 - 
	
Start metal enclosure for stairs #3.
 - 
	
Start metal framing along north canopy and line A.
 
Looking Forward
- 
	
Finalize pre cast and brick work along G line, from lines 8 to 17.
 - 
	
Continue metal framing work along north canopy and line A.
 - 
	
Continue MEP equipment installation in penthouse.
 - 
	
Continue slab on grade pouring at the east side of the building.
 - 
	
Continue back filling on the east side of the building.
 - 
	
Start metal enclosure for stairs #3.
 
Williams Hall
Work in Progress
- 
	
Continue concrete final painting on the north side of the building.
 - 
	
Continue with CW work in tunnel.
 - 
	
Start installation of the mechanical curbs in basement.
 - 
	
Start installation of the switch gear in electric room.
 
Looking Forward
- 
	
Finalize final painting concrete.
 - 
	
Continue with steam station work in mechanical room.
 - 
	
Continue with CW work in tunnel.
 - 
	
Continue with plumbing underground work.