91ֿ

News

4/7- Smith Hall Renovation Updates

April 7, 2016

Work in Progress: Pulling wire throughout for branch circuits. Installing duct on 1st floor. Complete domestic water rough-in on the 2nd floor. Sanitary piping rough-in has been completed on the 3rd floor. Completing remaining framing throughout. Starting door frame…

Read More »

4/7- ISB/Williams Hall Construction Updates

April 7, 2016

Work in Progress: Forming lift 3 on elevator #1. Working on retaining wall progressing south to column line A7. Pile caps and foundations for elevator #2 are complete. Looking forward: Pour lift #3 on elevator #1 on 4/8/2016. Steel delivery and erection begins for…

Read More »

91ֿ Holds Symposium on “The Neuroscience of the Social Brain” on April 7-8

March 31, 2016

91ֿ’s fourth annual Neuroscience Symposium will cover the latest research findings on “The Neuroscience of The Social Brain” on April 7-8 at the 91ֿ Hotel and Conference Center located in downtown Kent, Ohio.

Read More »

Becoming a Rocket Scientist

March 31, 2016

Theresa Benyo already had an exciting and fulfilling career as a project manager at NASA. With a great job, a house, a husband, two kids, and hobbies like musical theatre what more could you want? Academically speaking, she’d already earned a dual bachelor’s degree in physics…

Read More »

3/24- Williams Hall/ISB Construction Updates

March 24, 2016

Work in Progress: Working on pile caps and grade beams.  Plan to start column line 17 (Southern most column line) next week. Started working on forming elevator #2 (South). Pouring elevator #1 second lift (North) today. Continuing the installation of the basement…

Read More »

3/24- Smith Hall Renovation Updates

March 24, 2016

Work in Progress: First floor restroom and offices duct layout is complete with HVAC piping and duct installation has begun. Room 101 & 104 electrical rough-in is at 90% complete. Machine Shop electric panel installed and completed on Saturday 3/19. Room 223 electrical…

Read More »

3/24- Cunningham Hall Renovation Updates

March 24, 2016

Work in Progress: Steam piping in the 3rd floor east mechanical room is 20% complete. Steam condensate lines for the steam station and AHU#1 are in progress. Started installation of piping and duct work from AHU#2 in the 3rd floor west mechanical room to the addition has…

Read More »

91ֿ Researchers Publish Breakthrough in Leading Scientific Journal

March 24, 2016

Senior Research Fellow Quan Li, Ph.D., and his research group at 91ֿ’s Liquid Crystal Institute®, in the College of Arts and Sciences, have published a research article in the March 17 issue of Nature that could lead to a variety of breakthrough device…

Read More »

3/17- Cunningham Hall Renovation Updates

March 17, 2016

Work in Progress: Chilled water service in the 3rd floor east mechanical room is 95% complete by EOB on 3/18.  Will be ready for cooling system startup on 4/15. Currently insulating the chilled water pipes in the 3rd floor wast mechanical room. Steam reducing station…

Read More »

3/17- Smith Hall Renovation Updates

March 17, 2016

Work in Progress: New restroom plumbing rough-in nearly complete. Sheet metal duct rough-in has begun on the first floor and the new restroom areas. Electrical floor boxes are 75% complete in 223. Sanitary drain and toilet carriers are complete in the second floor. 3rd…

Read More »