Work in Progress:
- Forming lift 3 on elevator #1.
 - Working on retaining wall progressing south to column line A7.
 - Pile caps and foundations for elevator #2 are complete.
 
Looking forward:
- Pour lift #3 on elevator #1 on 4/8/2016.
 - Steel delivery and erection begins for sequence #1 on 4/11/2016 (North side – column line 0).
 - Continue with retaining wall south from column line A7 and turn east.
 - Start forming elevator #2 (south).