Work in Progress:
- Augarcast pile installation is complete.
 - Grade beams and pile caps are ongoing. Currently complete along column line 1 on the North and working south.
 - Started forming basement retaining wall along column line 1.
 - Forming of Elevator #1 (North) hoistway walls has begun.
 
Looking ahead:
- Continue grade beam and pile cap installation working south.
 - Pour basement retaining wall scheduled for 3/4/2016.
 - Pour first lift of north elevator hoistway schedule for 3/8/2016.