Work in Progress:
- Working on pile caps and grade beams. Plan to start column line 17 (Southern most column line) next week.
 - Started working on forming elevator #2 (South).
 - Pouring elevator #1 second lift (North) today.
 - Continuing the installation of the basement concrete retaining wall along column line 'A' between A7 and A10.
 - Currently 45% complete with pile caps.
 
Looking forward:
- Complete auger cast piles on column line 0 (North).
 - Steel erector mobilization to start on 3/28/2016. Steel bearing clips will begin on 3/28/2016 on concrete retaining walls.
 - Pour lift #3 on elevator #1 (North) on 3/30/2016.
 - Continue pile cap forming and pouring.