Work in progress:
- Augercast pile installation continues in the SE corner of the site. Currently 315 piles have been installed and 30 remain.
 - Pile cap and grade beam forming and installation has begun.
 - Basement retaining walls forming to begin 2/25/16.
 - Elevator #1 (North) concrete hoistway walls to begin 2/25/16.
 
Looking Forward:
- Complete augercast pile installation on 2/29/16.
 - Continue with pile caps and grade beams along column line 'A' (West side).
 - Continue with forming and placement of elevator #1 hoistway walls.
 - Continue with basement retaining walls following behind grade beams along column line 'A' north to south.