Work in progress:
- Augercast pile installation continues in the SW corner of the site and elevator #2 (South Elevator). Currently 215 piles have been installed and 130 remain.
 - Grade beams and pile caps forming and reinforcing in place for a first pour scheduled for Saturday, February 20th.
 - Excavation for elevator pit #1 (North Elevator).
 
Looking forward:
- Start formwork for concrete basement retaining walls on the north side.
 - Continue pile caps and grade beams.
 - Start forming elevator pit #1 walls.